

Video transcript can be found here.
Click to enlarge.
The project team drafted the following preliminary purpose statement that can be further developed as the project study progresses. The intent of this statement is to:
To preserve transportation assets, provide for the reliability and efficiency of the transportation system, and provide consistency with transportation planning along I-29 mainline from Exit 73 to Exit 68 and on CH110 through the Exit 71 interchange.
The primary "drivers" of the project and reflect the fundamental reasons why the project is being pursued.
Traffic operations: Forecasted traffic volumes indicate capacity needs on I-29 mainline and at the Exit 71 interchange through the 2050 Planning Horizon. The identified need from the planning process is a capacity deficiency, requiring that I-29 mainline and the Exit 71 interchange operate at least at a LOS “C” in urban areas and “B” in rural areas. The expected 2050 traffic volumes will cause segments of I-29 to operate at LOS “D” in urban areas and LOS “C” in rural areas and Exit 71 interchange ramp terminal intersections to operate at LOS “F”.
Road surface conditions: Based on the pavement condition survey of I-29 through the study area, the SDDOT Pavement Management System indicates a need to bring I-29 pavement condition rating to an acceptable level to accommodate the current and projected travel load.
Additional needs that are desirable, but not the core “drivers” of the projec.
Safety: Crash trends supporting a need for improvement include the Exit 71 southbound ramp crash rate exceeding the critical crash rate and multiple injury crashes, including one fatality, at the Exit 71 southbound ramp terminal. Along I-29, the proportion of rear-end crashes through the study area is approximately two times the percentage of rear-end crashes throughout all of I-29 in South Dakota.
Current design standards: Existing Exit 71 geometric elements, including intersection and stopping sight distance, shoulder width, vertical curve geometry, slopes, and ramp junction taper rates, support improvement to meet current SDDOT Road Design Manual guidelines.
Desired project outcomes beyond the transportation issues identified in the Purpose & Need and balance environmental & transportation values.
Goal 1: Accommodate Sioux Falls MPO Multi-Use Trail Study and local municipality bike plans
Goal 2: Regulatory compliance
Goal 3: Avoidance and minimization of environmental impacts, or enhancement opportunities
Daily and peak hour (morning and afternoon commute periods) traffic volumes were developed for three analysis scenarios:
The two future-year scenarios account for expected increases in traffic volumes passing through the study area and anticipated development.
Click to enlarge.
Using the existing and forecasted traffic volumes, study area intersections and roadway segments were analyzed to identify future capacity improvement needs in terms of Level of Service (LOS).
Click to enlarge.
Level of service (LOS) is a quantitative stratification of performance measures representing quality of service, or how well a transportation facility operates from a traveler’s perspective.
Click to enlarge.
Click to enlarge.
Click to enlarge.
This map shows some of the known resources adjacent to the I-29/Exit 71 Interchange project area. In the upcoming months, the project team will be conducting more detailed field studies to analyze and minimize impacts to biological, cultural, and socioeconomic resources such as:
Click to enlarge.
The I-29 Exit 71 compressed diamond interchange alternatives consist of:
Compressed Diamond Interchange – I-29 Under
Click to enlarge.
Compressed Diamond Interchange – I-29 Over
Click to enlarge.
The I-29 Exit 71 SPI alternatives consist of:
SPI – I-29 Under
Click to enlarge.
SPI – I-29 Over
Click to enlarge.
The I-29 Exit 71 DDI alternatives consist of:
DDI – I-29 Under
Click to enlarge.
DDI – I-29 Over
Click to enlarge.
The 273rd Street corridor was further evaluated with varying degrees of southward alignment shift through the interchange to address the following goals:
The following options were developed for the Compressed Diamond interchange (I-29 under) alternative but have elements applicable to all interchange type.
Note: With each of these options, there would be varying levels of risk of southbound Kenworth Place queues blocking access to the frontage road intersection. If a rearage road connection is feasible to the north between Irownworks Avenue and Kenworth Place, a frontage road would likely not be required. A rearage connection would address the increased separation goal (Goal 2) by providing ample distance between intersections.
Option 1: 6’ Offset
New bridge constructed 6’ south of existing bridge
Click to enlarge.
Benefits
Drawbacks
Option 2: 55’ Offset
New bridge constructed 55’ south of existing bridge
Click to enlarge.
Benefits
Drawbacks
Option 3: 80’ Offset
New bridge constructed 80’ south of existing bridge
Click to enlarge.
Benefits
Drawbacks
SDDOT is planning to reconstruct I-29 through the study area as part of the I-29 Exit 71 interchange project. Preliminary plans include:
One of this study’s goals is to determine whether I-29 through and south of Exit 71 needs to include all 6 lanes with the interchange project or whether the preliminary plan of paving 4 lanes now and adding the 3rd lane in each direction when needed will meet future needs.
Click the images below to enlarge.
Exit 68 to Exit 71 (4-lane)
Exit 68 to Exit 71 (6-lane)
Exit 71 to Exit 73 (6-lane to 4-lane transition)
Exit 71 to Exit 73 (6 lane)
Exit 73 to Exit 74 (6 lane)
Option 1
Reconstructs I-29 on the existing alignment with the new 3rd lane in each direction added to the inside median. New median width is 36’.
Click to enlarge.
Option 2
Realign I-29 outside of the RPZ to the east. Exhibits a 36’ median width to match I-29 to the north
Click to enlarge.
Option 3
Realign I-29 outside of the RPZ to the east. Exhibits a 60’ median width to match I-29 to the south.
Click to enlarge.
The 273rd Street (Lincoln County Highway 110) conceptual layouts reflect potential future improvements to illustrate what the future corridor might look like in conjunction with the planned SDDOT I-29 Exit 71 reconstruction. While these improvements are based on identified transportation needs through this study’s 2050 Planning Horizon, they are considered conceptual with regard to extent of modifications on 273rd Street and implementation timeframe.
Click to enlarge.
Preliminary ITS elements being considered as part of this study are shown in the figure. Recommendations from this study will be used as a guide to implement technologies as part of the planned I-29 Exit 71 interchange and I-29 mainline reconstruction project, other future corridor projects and/or SDDOT statewide ITS programs.
Preliminary Intelligent Transportation Systems (ITS) elements being considered as part of this study are shown in the figure. Recommendations from this study will be used as a guide to implement technologies as part of the planned I-29 Exit 71 interchange and I-29 mainline reconstruction project, other future corridor projects and/or SDDOT statewide ITS programs.
Proposed Variable Speed Limit (VSL) sign locations south of I-29 Exit 71 would be part of a larger I-29 corridor VSL implementation. The full extent of this implementation beyond the study area and specific VSL sign locations will be identified outside of this study. This figure illustrates how those elements could would fit within the planned SDDOT I-29 Exit 71 interchange and I-29 mainline reconstruction project.
Click to enlarge.
Today, please provide feedback on the revised I-29 Exit 71 interchange and I-29 mainline alternatives, evaluation, preliminary considerations for construction to help develop final recommendations for the study. Comments will be accepted until December 17, 2021.
The comment period for this meeting has ended. If you would like to leave a general comment, please use the comment form on the project website.
This will be the final public meeting of the Interchange Modification Study if the National Environmental Policy Act (NEPA) classification is determined to be a Categorical Exclusion (CE). If an Environmental Assessment (EA) is required, a third public meeting will be held during the summer/fall 2022.
Jon Wiegand, P.E., PTOE, Consultant Project
Manager
[email protected] |
Steve Gramm, P.E., SDDOT Project Manager
[email protected] |
The comment period for this meeting has ended. If you would like to leave a comment, please use the comment form on the project website.